Lawwly

Solar Applications Engineering, Inc. v. T.A. Operating Corporation

Supreme Court of Texas

327 S.W.3d 104 (2010)

Relevant factsFree

Under its construction contract with TA (defendant), Solar (plaintiff) was to submit a final application for payment accompanied by a lien-release affidavit after completing a punch list; a dispute arose over required punch-list items, TA and subcontractors filed liens, TA terminated the contract, and Solar submitted its final payment application without the lien-release affidavit, prompting TA to refuse payment on the theory that the affidavit was a condition precedent Solar had failed to satisfy. The trial court awarded Solar damages, but the appellate court reversed, finding the affidavit requirement was a condition precedent.

IssueFree

Whether a court determining if a contractual term is a condition precedent must ascertain the parties' intent by examining the entire contract.