Lawwly

Questar Builders, Inc. v. CB Flooring, LLC

Maryland Court of Appeals

978 A.2d 651 (Md. Ct. App. 2009)

Relevant factsFree

After a design change increased CB Flooring's (plaintiff) costs and CB requested a substantial price adjustment, Questar (defendant) solicited a rebid from a previously outbid competitor before CB even responded to the change, then terminated CB's contract, citing both an alleged breach and its unqualified right to terminate for convenience under the contract; the trial court found CB had not breached and that Questar had not properly invoked the termination-for-convenience clause.

IssueFree

Whether a termination-for-convenience clause is enforceable.