Eker Brothers, Inc. v. Rehders
New Mexico Court of Appeals
150 N.M. 542 (2011)
Relevant factsFree
Eker Brothers (plaintiff), hired as a concrete subcontractor by Rehders (defendant), performed $74,964.05 worth of contracted work but did not complete the full job; Rehders never paid for the completed work and spent an additional $42,448.20 to finish the concrete work elsewhere. Eker sued for payment; the trial court found Eker's breach was willful, material, and anticipatory, and on that basis barred Eker's claim entirely, awarding Rehders judgment for its extra completion costs. Eker appealed.
IssueFree
Whether a party that has breached a contract is entitled to restitution for the value of benefits conferred on the nonbreaching party that exceeds the damages the nonbreaching party suffered.